Contractor invoice template, with a filled progress billing example

Guide · Reporting, billing and back officeMcGuire Flanigan · Updated November 24, 2026 · 11 min read

A contractor invoice template should include your business name and license number, the client and job address, invoice number and dates, the contract reference, line items by phase, approved change orders, retainage held, payments received, the amount due, payment terms and a lien waiver note.

A contractor invoice template needs your business name, license number and contact details, the client and job address, an invoice number and dates, the contract reference, a line for each phase or item with labor and materials, any approved change orders, retainage held, payments received, the balance due, payment terms and a lien waiver note.

Below is the blank template as a table you can copy into a spreadsheet, word processor or your invoicing software, followed by a filled example of a progress invoice for a kitchen remodel. (Pricing the job before you bill it? See the roofing estimate template for how an estimate form is laid out.) After that: how progress billing and retainage work on the invoice, how to show change orders, where lien waivers fit, payment terms, the mistakes that slow payment down, and how software fills most of this for you.

What should a contractor invoice include?

A contractor invoice does two jobs. It asks for money, and it records what was agreed and what was done. A job billed in stages needs more than a one-day repair, because the client, lender or accountant will check each invoice against the contract. If your invoice doesn't line up with the contract, it sits on someone's desk until it does.

The fields fall into five blocks:

  • Who: your legal business name, license number, address, phone and email, and the client's name, billing address and the job address (which is often different).
  • Which job: invoice number, invoice date, due date, contract or project number, and the billing period for a progress invoice.
  • What was done: line items by phase or by item, each with a description, quantity or percent complete, rate and amount. Labor and materials either split out or rolled into the contract line, depending on the contract type.
  • What changed: approved change orders, each with its number, date approved and amount.
  • What's owed: subtotal, tax where it applies, retainage held, payments already received, the amount due now, payment terms and how to pay.

Contractor invoice template (copy this)

Each row is a field. Fill the middle column in once for your business, then reuse it on every job.

FieldWhat to enterExample
Business name and logoYour legal business name as registered, plus any trade nameBrightline Builders LLC
License numberYour state contractor license number, if your state issues oneLic. #000000 (placeholder)
Contact detailsOffice address, phone, billing email412 Mill St, Springfield; (555) 010-2200; billing@example.com
ClientName and billing address of the person or company that signed the contractDana and Chris Ortiz, 88 Elm Ave
Job addressWhere the work is, if different from billingSame as billing
Invoice numberA unique number that never repeats; many contractors prefix it with the job number2611-03
Invoice date and due dateThe date you issue it and the date payment is due under your termsNov 24 / Dec 9
Contract referenceContract number or date, and the original contract amountContract dated Sep 8; $48,000
Billing period or draw numberFor progress invoices: which draw this is and the work period it coversDraw 3, Oct 25 to Nov 21
Line itemsPhase or item, description, percent complete or quantity, rate, amountCountertops, 100 percent, $9,000
Change ordersChange order number, approval date, short description and amountCO #1, approved Oct 30, +$2,350
Subtotal and taxWork billed this period, and sales tax if your state taxes it$22,200; tax per contract
RetainagePercent held under the contract, amount held this invoice, total held to date5 percent; $1,110; $2,137.50 to date
Payments receivedDeposits and earlier draws already paid$19,522.50 on Draws 1 and 2
Amount due nowWhat the client pays on this invoice$21,090.00
Payment termsDue date rule, accepted methods, late fee if your contract has oneNet 15; ACH, check or card
Lien waiver noteWhich waiver you'll provide and whenConditional progress waiver attached
Signature or approval lineOptional: client or lender sign-off on the percent completeApproved by: ______ Date: ______

Filled contractor invoice example: kitchen remodel, Draw 3

This is a made-up example with invented names and numbers, set up the way a schedule-of-values progress invoice usually looks. Copy the layout, not the figures.

Brightline Builders LLC, Invoice 2611-03, dated November 24, due December 9. Client: Dana and Chris Ortiz. Contract dated September 8, original amount $48,000. Revised contract with Change Order 1: $50,350. Retainage under the contract: 5 percent of each draw, released at final completion.

ItemScheduled valuePercent completePreviously billedThis period
Demolition and haul-off$4,500.00100%$4,500.00$0.00
Rough plumbing and electrical$7,800.00100%$7,800.00$0.00
Drywall and paint$5,200.0050%$0.00$2,600.00
Cabinets, supplied and installed$16,500.00100%$8,250.00$8,250.00
Countertops, templated and installed$9,000.00100%$0.00$9,000.00
Flooring$5,000.000%$0.00$0.00
Change Order 1: pantry outlet and under-cabinet lighting (approved Oct 30)$2,350.00100%$0.00$2,350.00
Totals$50,350.0085%$20,550.00$22,200.00
SummaryAmount
Work billed this period$22,200.00
Less retainage held this period (5%)($1,110.00)
Amount due on this invoice$21,090.00
Total completed to date$42,750.00
Total retainage held to date$2,137.50
Balance to finish, plus retainage$7,600.00 + $2,137.50

Notes on the example: Draws 1 and 2 billed $20,550 of work, of which $1,027.50 was held as retainage, so $19,522.50 has been paid. Tax isn't shown separately because this example contract prices materials tax-included; your state's rules decide whether you do the same. Terms: net 15 by ACH, check or card. A conditional waiver on progress payment for this draw is attached and becomes effective when payment clears.

How do you bill progress payments on a contractor invoice?

Progress billing means you invoice a share of the contract as work gets done, instead of one bill at the end. There are two common ways to set it up, and the contract should say which one you're using.

  • Milestone draws: fixed amounts tied to events, such as a deposit at signing, a draw at rough-in inspection, a draw at cabinets installed and the balance at final walkthrough. Easy for homeowners to follow.
  • Schedule of values: the contract is broken into line items with a dollar value each, and every invoice bills the percent complete on each line, like the example above. Lenders, commercial clients and general contractors billing a property owner usually expect this.

Either way, the invoice should show three numbers for the whole job: the contract total, what's been billed so far, and what's left. A client who can see the balance to finish on every invoice asks fewer questions and approves draws faster. Never bill ahead of the work. If the percent complete on your invoice doesn't match what the client sees on site, you'll be explaining it on the phone instead of getting paid.

What is retainage and how do you show it?

Retainage (also called retention) is a percentage of each progress payment the client holds back until the job is finished, as security that punch-list items get done. The percentage comes from your contract, and some states cap it or set rules for when it must be released, especially on public work. Check your state before you agree to a number.

On the invoice, show retainage in three places: the amount held on this draw, the total held to date, and a line that says when it will be released. Treat retainage as money owed to you, not money gone. The most common place contractors lose it is the final invoice, when nobody remembers to bill it. Put a separate "retainage release" invoice on your closeout checklist.

How do you show change orders on an invoice?

A change order is a signed change to the scope or price of the contract. On the invoice, give each approved change order its own line with its number, the date it was approved and the amount, and add it to the contract total so the revised contract amount is visible. Bill change-order work the same way you bill the rest: by percent complete or on completion.

Two rules save most disputes. First, only invoice change orders the client signed before you did the work. A verbal "go ahead" from the homeowner in the driveway is how a $2,000 extra turns into a $2,000 argument. Second, never fold extra work into an existing line to make it look smaller. A line that suddenly costs more than its scheduled value invites the client to question every other line.

Where do lien waivers fit with a contractor invoice?

A lien waiver is a document in which you (or your subcontractors and suppliers) give up lien rights for work that's been paid for. Owners and lenders often ask for one with every draw, so it helps to state on the invoice which waiver comes with it.

California is a good example of how specific this gets. The state's Contractors State License Board explains that there are four waiver types: conditional and unconditional, each for progress and final payment, and that to be effective they must substantially follow the forms in Civil Code sections 8132, 8134, 8136 and 8138. A conditional waiver only takes effect once you're actually paid, which is why it's the one to send with an invoice. You sign the unconditional version after the money clears. The CSLB page also points out that paying the prime contractor doesn't guarantee subs and suppliers were paid, which is why clients ask for their waivers too.

Other states use different forms, and some have no statutory form at all. This isn't legal advice. Check your state licensing board or a construction attorney for the form and timing that applies to you, and for any preliminary notice deadlines on your jobs.

What payment terms should a contractor use?

Put your terms in the contract first, then repeat them on every invoice. The ones contractors use most:

  • Deposit at signing, credited on the first progress invoice. Some states limit how much a home-improvement contractor can collect up front, so confirm your state's limit.
  • Net 7, net 15 or net 30 on progress draws. Shorter terms work for homeowners; commercial clients often run their own payment cycle no matter what your invoice says, so ask about it before you sign.
  • Due on completion for small jobs and the final punch-list draw.
  • Late fee, only if the contract includes one and your state allows it. A late fee that isn't in the contract is hard to collect.

List every payment method you accept and how to use it (payment link, ACH details, who to make checks out to). The fewer steps between reading the invoice and paying it, the sooner you're paid.

Common contractor invoice mistakes

  • No contract reference. The client's accountant can't match the invoice to anything, so it waits.
  • Billing unsigned change orders. It turns a payment into a negotiation.
  • Percent complete that doesn't match the site. One inflated line makes the client re-check the whole draw.
  • Forgetting retainage at closeout. The last slice of a job is often where the profit sits.
  • Missing license number or legal name. Some states require the license number on contracts and related documents, and commercial clients often reject invoices from a name that doesn't match the contract.
  • Waiver mismatch. Sending an unconditional waiver before you're paid gives up rights you can't get back.
  • Sending it late. An invoice sent two weeks after the draw milestone pushes your payment back two weeks.

How to send a contractor invoice and follow up

Send each draw the day the milestone is reached, by email with a PDF and a payment link, and copy anyone the contract names (a lender's draw administrator, a property manager). Attach the supporting documents the client will ask for anyway: photos of the completed phase, the signed change order and the conditional waiver.

A follow-up rhythm that works for most contractors: a short reminder two or three days before the due date, a polite nudge the day after it's due, and a phone call (not another email) after a week. If a draw is late because the client disputes part of the work, deal with the dispute first; a reminder sequence on a disputed draw only hardens positions. Our guide to an AI agent for overdue invoices covers how to tell a late payer from a disputed job before anyone sends a reminder.

How invoicing software fills these fields automatically

Most of the template above is data you already typed somewhere else: the client, the job address, the contract amount, the change orders. Invoicing and field service software pulls it into the invoice so nobody retypes it.

What software doesn't do on its own is notice what's missing: the job closed with no final invoice, the retainage that was never billed, the change order done but not signed. That's checking across systems, and it's where people or an agent come in. If the problem is supplier bills coming in rather than invoices going out, see AI invoice processing for small business.

Where Cortex fits

Cortex builds AI agents that work inside the software you already run, such as QuickBooks or Jobber. For a contractor, that might be one agent that checks every closed job each night for a missing final invoice, unbilled retainage or an unsigned change order, then drafts the invoice or the reminder for your office to review. Each agent has one job, uses its own login with the least permission it needs, and a person approves anything that goes to a client. If you're happy billing from a template and your draws go out on time, you don't need us. If they don't, start with the free AI operations audit, or see how we work with contracting businesses.

AI for general contractors

Sources

  1. 01Conditional and Unconditional Waiver and Release Forms, California Contractors State License Board
  2. 02Set up and send progress invoices in QuickBooks Online, Intuit QuickBooks
  3. 03Invoicing Software, Jobber
  4. 04Automations, Jobber Help Center

Questions operators ask

What is the difference between a contractor invoice and an estimate?

An estimate or bid is sent before the work and says what the job will cost. An invoice is sent after work is done (or a stage is reached) and asks for payment. On a progress job you send one contract and several invoices, each billing the share of work completed.

How do I invoice for a progress payment?

List each phase or line from the contract with its scheduled value, the percent complete, what was billed before and what you are billing now. Subtract any retainage, show payments received, and state the amount due. Attach photos, signed change orders and a conditional lien waiver if the client requires one.

Should a contractor invoice include a license number?

Include it if your state issues contractor licenses. Some states require the license number on contracts, bids and related documents, and it helps clients and lenders confirm who they are paying. Check your state licensing board for the exact rule.

How do I show retainage on an invoice?

Show the retainage percentage from the contract, the amount held on this invoice, the total held to date, and when it will be released. Then send a separate retainage release invoice at final completion so the held amount does not get forgotten.

Can I use a free contractor invoice template in Word or Excel?

Yes. The table on this page works in Word, Excel or Google Sheets. A spreadsheet is better for progress billing because it can total the previously billed and this period columns for you. Once you send more than a few invoices a week, invoicing software saves the retyping.